Wards 13, 14, 15 - Jan. 2008 Update on Ferry Street Bridge Work
(1/7/2008) Monthly update JANUARY, 2008
Period: 01/01/08 to 01/31/08
Project 92-582 - Reconstruction of the Ferry Street Bridge
New Haven, Connecticut
Contractor: Cianbro Corp. of Pittsfield, Maine
Contract Amount: $16,628,417
Overall Schedule
• Start Date: August 21, 2006
• Scheduled Completion Date: February 5, 2009
• Percent complete: 83% (Estimated by payments)
• Total Number of Days: 900
• Current number of Days: 509
• Changes to Schedule: None
Work in progress/completed in the past month
• Installed Submarine Cable between Pier #1 & #2
• Install new concrete fender cap (South East fender)
• Demolition of Steel Deck at Bascule Span (South Span)
• Install Steel at South Bascule Span
• Terminate new submarine cables
• Install Pier #1 fender system (South West)
• Bearing Repairs North Pier
Work to be performed in the next month
• Pile driving Pier #1 fender system (South West)
• Bearing Repairs North (Pier #2 NE/NE)
• Erect Channel Timber Pier #1
• Install Steel at South Bascule Span
Hours of Operations
• Current work hours are: Daytime 6:30am to 5:00 pm, Monday through Friday; No Night work. Some Saturday work 7am to 5:00 pm.
If you have any questions or concerns regarding the construction activities above please call Paul Ezigbo at the Connecticut Department of Transportation Field Office (203) 508-1388.
Submitted by: C Paul Ezigbo 1/11/07
Follow this link for more information.